2021 North Cedar Streetscape Project and other various Downtown Improvements are underway!
As work continues, you can watch the progress as it takes place via the Downtown Owatonna Live Camera Stream any time by clicking here for the YouTube site or by visiting our 2021 North Cedar Ave Streetscape Project page!
9/10/2021 - ISG Update:
Work This Past Week
- An additional crew began working within the project extents
- The storm sewer was installed within the Pearl Street intersection
- The watermain is being installed within the Pearl Street intersection
- Permanent water services are being connected along the 300 block to the buildings
- Drain basins are being installed at mid-block to provide drainage in the planting areas
and alleys
Upcoming Work
- The additional crew will continue to be on-site as the project progresses
- Bituminous paving will occur in the alley next to 107 West Rose Street to reestabilsh the parking stalls
- Water service installation will continue along the 300 block
- Some building access may be necessary to confirm services, and communication with businesses will continue to occur as required
Additional removals within the 200 block are anticipated the week of September 20th and concrete paving on the 300 block is anticipated to begin the week of September 27th
For updates from ISG regarding this project, visit ISG's Project Website, scroll to "Stay Connected" and fill out the form titled "Sign up here for project updates"