Wastewater Treatment Facility Expansion

Capacity increase means being prepared for Owatonna’s future growth

Construction of the Wastewater Treatment Facility Upgrade and Expansion has been progressing since July 2022. 

The project is expected to be completed in 2025. An expansion of Owatonna’s existing wastewater treatment plant was initiated in 2017. The plant has been operating at or above its capacity for the past several years. In 2021, plans got underway to expand the plant from its current capacity of five million gallons per day (MGD) to more than nine MGD, an 80 percent increase to continue meeting the needs of the growing community. 

The project’s original completion date of the end of 2024 has been delayed to 2025 largely due to supply chain issues with electrical components.