Engineering Updates 10/22/2021

Posted on October 26, 2021 at 2:49 PM by Jeanette Clawson

City of Owatonna Engineering

Construction has begun and various projects can be seen around The City of Owatonna. Please slow down and use caution when approaching a construction zone.
 
 We thank you for your patience as these projects are completed. 

 
2021 Construction Projects:
2021 Project Location Map

 2021 Bridge Street: 

Work this Past Week  

   Work this week included concrete mainline and roundabout paving, trimming and setting forms. The new concrete typically takes between 7 and 14 days

before it can be driven on so please use extra caution while paving is occurring, follow detours and do not enter the area until the road is open to traffic.

    Next week work is planned to include continued concrete paving including curb and gutter as well as driveway paving. Temporary lighting and seeding is to be

placed over the next couple weeks as well. The paving is expected to continue for about 1.5 weeks to pave the remainder of Phase 1A and Phase 2, including the

curb and gutter and sidewalk. Following this, the concrete typically takes between 7 and 14 days before it can be driven on so please use extra caution

while paving is occurring and do not enter the area until the road is open to traffic.

    The intersection of Park Drive and W. Bridge street is open to three directions of traffic, with the north, east and south legs open to both directions of traffic

and the west leg closed to traffic during this phase of the project. Some work will continue to occur along the roadway and at the Park Dr intersection as needed.

Please continue to use caution and follow the detour routes as work will continue to finalize Phase 1 and progress Phase 2.

    This project is phased and is anticipated to generally follow the phasing plan as shown in the image below. Currently, the contractor is performing work within a

portion of “Construction Phase 1A” and “Construction Phase 2” areas as outlined in pink and green, respectively.

    Please feel welcome to contact Reese Sudtelgte or Anthony Lance of ISG with any questions regarding the project or any other items of concern.

To sign up for updates specific to the 2021 Bridge Street Project, please visit Notify Me.

2021 N Cedar Streetscape

Within the 300 Block

    • The concrete was poured for the remaining sidewalk along the east side of the street.
    • The concrete curb and gutter was placed.
    • The roadway base is being prepared for the Pearl Street intersection pavement.
  • Within the 200 Block
    • Water service connection to buildings has occurred through most of the block.
    • The storm sewer has been installed on the north half of the block.
    • Additional removals are occurring at the Vine Street intersection.

Upcoming Work

  • Within the 300 Block
    • Mainline pavement is anticipated to occur next week.
      • The new concrete typically takes between 7 and 14 days before it can be driven on. Please use extra caution while paving is occurring, and do not enter the area until the road is open to traffic.
      • The contractor is planning to construct the concrete curb and gutter within the Pearl Street intersection next week.
  • Within the 200 Block
    • Installation of the sanitary sewer manhole within the Vine Street intersection is anticipated on Monday.
      • This will require use of the bypass pump at Broadway Street and will cause traffic changes within the 100 block for approximately one day. The contractor will be coordinating with these businesses. 
    • The contractor plans to connect the watermain to the mainline within Vine Street.

The storm sewer installation on the south half of the block is anticipated to follow.

The Owatonna Downtown Live Stream can be found on The 2021 North Cedar Ave Streetscape Project page! Be sure to visit the website for detour routes and alternate parking areas.

To sign up for updates for the North Cedar Streetscape Project, please visit the ISG Project Page, scroll to "Stay Connected" and fill out the form titled "Sign up here for project updates"

2021 Truman Avenue: 


26th Street & State Avenue Roundabout: 